Question: A project manager has been managing a long term training project. The training is over, and she is trying to close out her project. The

A project manager has been managing a long term training project. The training is over, and she is trying to close out her project. The situation is not good.

Although all requirements have been met, the customer is not satisfied. The customer states that the results of the training were not what they expected. One likely cause of this was:

a. the instructors were not qualified

b. the customer’s expectations were not turned into requirements

c. the customer is trying to exploit the contract

d. the training did not go into enough detail

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Management Communication Questions!