Question: A project manager has submitted several contested changes to the customer. These contested changes, often called claims or disputes, are impeding progress. The preferred method
A project manager has submitted several contested changes to the customer.
These contested changes, often called claims or disputes, are impeding progress.
The preferred method to settle claims and disputes is:
a. mediation
b. arbitration
c. litigation
d. negotiation