Question: Many models exist for stakeholder analysis. However, our sponsor has requested that we use the salience model to initiate the project. This particular model views
Many models exist for stakeholder analysis. However, our sponsor has requested that we use the salience model to initiate the project. This particular model views stakeholders on the basis of:
a. legitimacy, power, and influence
b. power, interest, and impact
c. influence, impact, and power
d. power, urgency, and legitimacy