Question: The project has entered the close project or phase process. Along with the organizational process assets updates another critical output is: a. verified deliverables b.

The project has entered the close project or phase process. Along with the organizational process assets updates another critical output is:

a. verified deliverables

b. final product, service, or result transition

c. accepted deliverables

d. procurement documents