Question: The project has entered the close project or phase process. Along with the project management plan and the organizational process assets another critical input is:

The project has entered the close project or phase process. Along with the project management plan and the organizational process assets another critical input is:

a. verified deliverables

b. final product, service, or result transition

c. accepted deliverables

d. issue logs

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Management Communication Questions!