Question: You are working on your first large-scale project. The projects CPI is .97. The project is running five weeks behind schedule and has over 300
You are working on your first large-scale project. The project’s CPI is .97.
The project is running five weeks behind schedule and has over 300 stakeholders.
Where should you, the project manager, increase your emphasis?
a. schedule
b. cost
c. stakeholder engagement
d. conflict management