Question: You are working with your core team developing the network diagram for your map making project. Your team member tells you that they suggest you

You are working with your core team developing the network diagram for your map making project. Your team member tells you that they suggest you plan in your schedule that you will do a fly over of the area before researching the geography.

You ask them why and they tell you it is a best practice. This is an example of a(n):

a. mandatory dependency

b. discretionary dependency

c. hard logic

d. external dependency