Question: You have been managing a large mapmaking project for the government. Your customer is asking for multiple scope changes. You are considering these requested changes

You have been managing a large mapmaking project for the government. Your customer is asking for multiple scope changes. You are considering these requested changes and trying to determine their true magnitudes. You are most likely to review what document?

a. scope management plan

b. WBS

c. project charter

d. cost management plan