Question: Your contractor is reporting cost performance to you on a monthly basis using CPI. History has shown that the projects CPI often becomes stable when

Your contractor is reporting cost performance to you on a monthly basis using CPI. History has shown that the project’s CPI often becomes stable when what percent of the work is complete?

a. 15%-20%

b. 25%-30%

c. 30%-45%

d. 30% -50%