Question: Your organization will be using earned value for the first time. You realize that different types of work packages should utilize different earned value measurement
Your organization will be using earned value for the first time. You realize that different types of work packages should utilize different earned value measurement methods. Work packages associated with equipment deliveries often use:
a. the 0/100 rule
b. the 20/80 rule
c. the 50/50 rule
d. the 100/0 rule