Question: Crane Inc. has decided to use the high-low method to estimate the total cost and the fixed and variable cost components of the total cost.
Crane Inc. has decided to use the high-low method to estimate the total cost and the fixed and variable cost components of the total cost. The data for various levels of production are as follows:

a. Determine the variable cost per unit and the fixed cost.
b. Based on part (a), estimate the total cost for 14,000 units of production.
Total Costs Units Produced $700,000 10,000 15,000 22,500 840,000 920,000