Question: Mary is using forecasting to determine her projects estimate at complete. What would be the most likely place to include this information? A. The communications
Mary is using forecasting to determine her project’s estimate at complete. What would be the most likely place to include this information?
A. The communications management plan.
B. The project activity report.
C. Project communications.
D. The stakeholder engagement report.