Question: Mary is using forecasting to determine her project's estimate at complete. What would be the most likely place to include this information? A. The communications

Mary is using forecasting to determine her project's estimate at complete. What would be the most likely place to include this information?

A. The communications management plan.

B. The project activity report.

C. ?he performance reports.

D. The stakeholder management report.