Question: 51. The critical path in a network is the path that: A. Has the greatest degree of risk B. Is the longest during the project

51. The critical path in a network is the path that:

A. Has the greatest degree of risk B. Is the longest during the project and determines its duration C. Must be completed before all other paths D. Has activities with float greater than zero