Question: 9. Preparing a stakeholder register and performing a stakeholder analysis are part of which knowledge area? A. project integration management B. project human resource management
9. Preparing a stakeholder register and performing a stakeholder analysis are part of which knowledge area?
A. project integration management B. project human resource management C. project stakeholder management D. project communications management