Question: Unknown problems such as escalation factors are often budgeted for using the: a. Project managers charge number b. Project sponsors charge number c. Management reserve

Unknown problems such as escalation factors are often budgeted for using the:

a. Project manager’s charge number

b. Project sponsor’s charge number

c. Management reserve

d. Configuration management cost account