Question: What do you know about this project? A. The EAC is a positive number, which means the project will finish under budget. B. You do
What do you know about this project?
A. The EAC is a positive number, which means the project will finish under budget.
B. You do not have enough information to calculate CPI.
C. The CV is a negative number in this case, which means you’ve spent less than you planned to spend as of the measurement date.
D. The CV is a positive number in this case, which means you’re under budget as of the measurement date.