Question: You are a project manager working on a software development project. Youve developed the risk management plan, identified risks, and determined risk responses for the

You are a project manager working on a software development project. You’ve developed the risk management plan, identified risks, and determined risk responses for the risks. One of the risks you identified occurs, and you implement the response for that risk. Then, another risk occurs as a result of the response you implemented. What type of risk is this called?

A. Trigger risk B. Residual risk C. Secondary risk D. Mitigated risk