Question: You are running a major project with four sub - projects. Each of the sub - project managers has developed a risk management plan, identified
You are running a major project with four subprojects. Each of the subproject managers has developed a risk management plan, identified many risks, analyzed them and planned for risk response.
It is now two months later. What should you not do
Make sure that the sub project managers keep track of the identifiechrisks and those on the watch list.
Make sure that the sub project managers monitor their project work for new and changing risks.
Make sure that the subproject managers monitor trigger conditions for contingency plans.
Ensure that they handle all risks to save you from project level risk control.