Question: Your team is working on creating a WBS for phase 2 of the ABC software implementation project. Which of the following is an example of
Your team is working on creating a WBS for phase 2 of the ABC software implementation project. Which of the following is an example of what might appear in the second level of your WBS?
A. ABC Software implementation project B. Project deliverables C. Project phases D. Activities