Question: A project begins on December 4, 2005. The project consists of three activities: activity 1, activity 2, and activity 3. Activity 2 can start the
A project begins on December 4, 2005. The project consists of three activities: activity 1, activity 2, and activity 3. Activity 2 can start the day after activity 1 finishes. Activity 3 can start the day after activity 2 finishes. Set up a worksheet that accepts as inputs the duration (in days) of the three activities and then produces both the month and the year during which each activity is completed.