Question: A building subcontractor submitted a bid for construction of a portion of a high-rise office building. The bid contained material computational errors. The general contractor
A building subcontractor submitted a bid for construction of a portion of a high-rise office building. The bid contained material computational errors. The general contractor accepted the bid with knowledge of the errors.
Which of the following statements best represents the subcontractor’s liability?
a. Not liable because the contractor knew of the errors.
b. Not liable because the errors were a result of gross negligence.
c. Liable because the errors were unilateral.
d. Liable because the errors were material.