Question: Ames Construction Co. contracted to build a warehouse for White Corp. The construction specifications required Ames to use Ace lighting fixtures. Inadvertently, Ames installed Perfection

Ames Construction Co. contracted to build a warehouse for White Corp. The construction specifications required Ames to use Ace lighting fixtures. Inadvertently, Ames installed Perfection lighting fixtures which are of slightly lesser quality than Ace fixtures, but in all other respects meet White’s needs. Which of the following statements is correct?

a. White’s recovery will be limited to monetary damages because Ames’ breach of the construction contract was not material.

b. White will not be able to recover any damages from Ames because the breach was inadvertent.

c. Ames did not breach the construction contract because the Perfection fixtures were substantially as good as the Ace fixtures.

d. Ames must install Ace fixtures or White will not be obligated to accept the warehouse.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Model Based Testing For Embedded Systems Questions!