Master Mfg., Inc. contracted with Accur Computer Repair Corp. to maintain Master’s computer system. Master’s manufacturing process depends on its computer system operating properly at all times. A liquidated damages clause in the contract provided that Accur pay $1,000 to Master for each day that Accur was late responding to a service request.

On January 12, Accur was notified that Master’s computer system failed. Accur did not respond to Master’s service request until January 15.

If Master sues Accur under the liquidated damage provision of the contract, Master will

a. Win, unless the liquidated damage provision is determined to be a penalty.

b. Win, because under all circumstances liquidated damage provisions are enforceable.

c. Lose, because Accur’s breach was not material.

d. Lose, because liquidated damage provisions violate public policy.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Model Based Testing For Embedded Systems Questions!