Question: The maximum time to complete a task in a project is 2.5 days. Suppose that the completion time as a proportion of this maximum is
The maximum time to complete a task in a project is 2.5 days. Suppose that the completion time as a proportion of this maximum is a beta random variable with 2 and 3.
What is the probability that the task requires more than 2 days to complete?