The maximum time to complete a task in a project is 2.5 days. Suppose that the completion

Question:

The maximum time to complete a task in a project is 2.5 days. Suppose that the completion time as a proportion of this maximum is a beta random variable with α = 3 and β = 2. What is the probability that the task requires more than 2 days to complete? (Note that α and β are different from your homework. With using the parameters of the homework problem, you would not earn any point.)