Question: Construct a Gantt chart for the project defined in Problem and Exercise 7. Problem and Exercise 7 A project has been defined to contain the

Construct a Gantt chart for the project defined in Problem and Exercise 7.

Problem and Exercise 7

A project has been defined to contain the following list of activities along with their required times for completion.Activity No. Immediate Activity Time (weeks) Predecessors 1 Collect requirements 3 2

a. Draw a network diagram for the activities.

b. Calculate the earliest expected completion time.

c. Show the critical path.

d. What would happen if activity 6 were revised to take 6 weeks instead of 2 weeks?

Activity No. Immediate Activity Time (weeks) Predecessors 1 Collect requirements 3 2 Analyze processes 2 1 3 Analyze data 2 2 4 Design processes 6 2 5 Design data 3 3 6 Design screens 2 3,4 7 Design reports 4 4,5 8 Program 5 6,7 9 Test and document 10 Install 72 7 8,9

Step by Step Solution

3.38 Rating (148 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To address the multipart question we will proceed as follows Understanding the Activities First lets list the activities their durations and their immediate predecessors based on the provided image Ac... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Modern Systems Analysis And Design Questions!