Question: Although there may be some perceived redundancy with the project charter, the PM assigned to your team, Bobby, asked for your assistance drafting a document
Although there may be some perceived redundancy with the project charter, the PM assigned to your team, Bobby, asked for your assistance drafting a document that outlines the scope, deliverables, exclusions, assumptions, and constraints associated with your project. You’re outlining:
a. A project scope statement
b. A project business case
c. A Preliminary project scope statement
d. A project requirements document