Question: Collaborating with Rhett, your project manager, you have logically decomposed the total scope of work related to the product in a hierarchical manner. What was
Collaborating with Rhett, your project manager, you have logically decomposed the total scope of work related to the product in a hierarchical manner. What was the output of your effort?
a. Process model
b. Work breakdown structure
c. Capability table
d. Salience Diagram