Question: Julius, a college intern, has inquired as to the differences between the requirements management plan and the business analysis plan. How would you best answer
Julius, a college intern, has inquired as to the differences between the requirements management plan and the business analysis plan. How would you best answer his question?
a. The requirements management plan is a subsidiary plan of the overall project management plan, whereas the business analysis plan is a complementary artifact.
b. The requirements management plan covers the project, whereas the business analysis plan is focused on the effort associated with business analysis.
c. Both documents are complementary artifacts.
d.The requirements management plan covers both the project and product, whereas the business analysis plan is focused on the effort associated with business analysis.