Question: Your Change Control Board recently voted on several requests; three were approved, two were denied, and one was deferred pending further information. Upon leaving the
Your Change Control Board recently voted on several requests; three were approved, two were denied, and one was deferred pending further information. Upon leaving the room with Finn, your project manager, you both agreed:
a. In your role as business analyst, you would only communicate the approved and denied requests.
Pending the outcome of the next meeting, you would share the decision on the deferred request.
b. Finn, as the project manager, would communicate the decisions on all requests to all stakeholders.
c. In your role as business analyst, you would communicate the decisions regarding all requests to all stakeholders.
d. Finn, as the project manager, would only communicate the decision regarding the deferred request, as representatives for the five requests were present.