Your project manager, Mila, is concerned about scope creep at both the project and the product level. To address this concern, you both agreed to institute a requirements traceable matrix. After the matrix is created and approved, what can you do to set boundaries?
a. Present the matrix to your stakeholders for approval on the approach.
b. Perform a dependency analysis.
c. Establish a process for monitoring and controlling scope.
d.Establish a baseline.