Question: Your software project is using an iterative methodology to validate whether the delivered solution is functional, based on a typical day. Elise, the subject matter

Your software project is using an iterative methodology to validate whether the delivered solution is functional, based on a typical day. Elise, the subject matter expert for the accounts payable group, participates in which of the following:

a. User acceptance testing (UAT)

b. Day-in-the-life (DITL) testing

c. Performance testing (PT)

d. Unit testing (UT)