Question: 19. A computer center has two identical computers for batch processing. The computers are used as parallel processors. Job times are estimated by the user,

19. A computer center has two identical computers for batch processing. The computers are used as parallel processors. Job times are estimated by the user, but experience has shown that an exponential distribution gives an accurate description of the actual job times. Suppose that at a point in time there are eight jobs remaining to be processed with the following expected job times (expressed in minutes):

Job 1 2 3 4 5 6 a 8 Expected time 4 8 | 50 1 30 20 6

a. In what sequence should the jobs be processed in order to minimize the expected completion time of all eight jobs (1.e., the makespan)?

b. Assume that computer A is occupied with a job that has exactly two minutes of processing time remaining and computer B is idle. If job times are deterministic, show the start and end times of each job on each computer using the sequence derived in part (a).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Operations And Supply Chain Management Questions!