Question: Use the Excel template Gantt Chart to develop a Gantt chart for the early start schedule for the wedding project in problem 36 in the
Use the Excel template Gantt Chart to develop a Gantt chart for the early start schedule for the wedding project in problem 36 in the Computational Problems and Exercises section. Explain and trace the project’s critical path(s).
Data from in Problem 36
Mary is planning her wedding and develops the following preliminary information.

Activity A (select wedding date) B (select wedding location) C (guest list, who's attending) D (select entertainment) E (choose catering) F (wedding day) Immediate Predecessor(s) A, B A A, C D, E Estimated Normal Time 3 weeks 4 weeks 4 weeks 3 weeks 2 weeks 0 weeks