Question: Consider that there is skill interchangeability, that is, the same workers can be used interchangeably in both the assembly lines. If the company is required
Consider that there is skill interchangeability, that is, the same workers can be used interchangeably in both the assembly lines. If the company is required to produce 500 units in a day, what would be the manpower requirement in an 8 hour working day with 20% fatigue allowance? Show your computation in terms of man-hours and man-day’s also.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts