Samantha and Levi Taylor are planning an anniversary party for their parents in December and they want it to have a holiday theme. They have identified the following planning activities and time estimates:

TIME ESTIMATE ACTIVITY ACTIVITY DESCRIPTION PREDECESSOR (DAYS) Set date 3 a b Reserve a location 5 Print and send a, b i


Construct the network for this project, identify the critical path and determine the project duration time.