Question: Mason Machine Tools is reevaluating its facility layout. The current layout is shown in Figure 10-13 and the fromto matrix is in Table 10-11. Mason
Mason Machine Tools is reevaluating its facility layout. The current layout is shown in Figure 10-13 and the from—to ‘matrix is in Table 10-11. Mason has to leave department C in its current location because relocation costs are too high. It is considering exchanging departments B and D. Evaluate the proposal by computing the /d score for both layouts.

FIGURE 10-13 Current layout for Mason Machine Tools. B A D C E F TABLE 10-11 From-To Matrix for Mason Machine Tools Department Trips between Departments ABCDEE F A B C D E F 5 20 5 30 20 1921 8 10 10 15 5 17