Question: The difference between a gross material requirements plan (gross MRP) and a net material requirements plan (net MRP) is: a) The gross MRP may not

The difference between a gross material requirements plan (gross MRP) and a net material requirements plan (net MRP) is:

a) The gross MRP may not be computerized, but the net MRP must be computerized.

b) The gross MRP includes consideration of the inventory on hand, whereas the net MRP doesn’t include the inventory consideration.

c) The net MRP includes consideration of the inventory on hand, whereas the gross MRP doesn’t include the inventory consideration.

d) The gross MRP doesn’t take taxes into account, whereas the net MRP includes the tax considerations.

e) The net MRP is only an estimate, whereas the gross MRP is used for actual production scheduling.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

c The net MRP includes co... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Operations Management 6th Questions!