The following is a list of activities/work packages and their precedence and duration, for a new-plant start-up
Question:
The following is a list of activities/work packages and their precedence and duration, for a new-plant start-up project. Draw the precedence network, calculate earliest and latest times, and determine the project duration and critical activities.
Solution:
Project duration = 17 months
Critical activities = B, E, H, K
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Operations Management
ISBN: 9781259270154
6th Canadian Edition
Authors: William J Stevenson, Mehran Hojati, James Cao
Question Posted: