The following is a list of activities/work packages and their precedence and duration, for a new-plant start-up

Question:

The following is a list of activities/work packages and their precedence and duration, for a new-plant start-up project. Draw the precedence network, calculate earliest and latest times, and determine the project duration and critical activities.

Activity/ Work Duration Packages Description Precedes (months) A Selection of plant manager 3 B Site survey and soil test 1 Extension of road, water, 6. utilities, sewer D Selection and purchase of A 2 equipment E Final plant design F Employee interviews and A 3. hiring G Equipment delivery 9.


Solution:















Project duration = 17 months


Critical activities = B, E, H, K