The following is a table of activities associated with a project at Bill Figg Enterprises, their duration

Question:

The following is a table of activities associated with a project at Bill Figg Enterprises, their duration and what activities each must precede:

The following is a table of activities associated with a

(a) Draw an AON diagram of the project, including activity duration.
(b) Define the critical path, listing all critical activities in chronological order.
(c) What is the project duration (in weeks)?
(d) What is the slack (in weeks) associated with any and all noncritical paths through theproject?