A film post-production company with six technical staff has accepted a project that must be completed within
Question:
A film post-production company with six technical staff has accepted a project that must be completed within ten weeks. There are seven activities involved, as detailed in Table 16.7.
(a) Draw a network diagram for the project.
(b) Will the company need to hire any temporary staff and if so, when and how many?
Step by Step Answer: