Question: A machine shop has seven jobs to be processed through a two-step process. The processing times in hours for each job for each operation are
A machine shop has seven jobs to be processed through a two-step process. The processing times in hours for each job for each operation are given in the following table. Determine the job sequence that will minimize the total time required to complete the jobs:

Step 1 Step 2 Job Processing Time Processing Time 1.50 1.00 2.40 1.70 1.40 1.20 1.90 1.70 1.80 2.00 1.60 2.00 1.55 1.70
Step by Step Solution
3.44 Rating (163 Votes )
There are 3 Steps involved in it
The op... View full answer