Another machine shop has five jobs to be processed through three operations: lathing, grinding, and drilling. The

Question:

Another machine shop has five jobs to be processed through three operations: lathing, grinding, and drilling. The hours required to process these jobs for each of the three operations are shown in the following table:

Lathing Grinding Drilling Job 5 2 3 3 1 2 4 1 LO Co


1. Sequence the jobs using the SPT and the LPT rules.

2. Prepare a Gantt chart for each operation for each rule.

3. Which rule is preferable, and why?