Another machine shop has five jobs to be processed through three operations: lathing, grinding, and drilling. The
Question:
1. Sequence the jobs using the SPT and the LPT rules.
2. Prepare a Gantt chart for each operation for each rule.
3. Which rule is preferable, and why?