Question: A project has the following activities, precedence relationships, and activity durations. Draw the AOA project network. How long would it take to complete this project?

A project has the following activities, precedence relationships, and activity durations. Draw the AOA project network. How long would it take to complete this project? What is the length of the critical path?

ACTIVITY A B D E F LL G H - IMMEDIATE PREDECESSOR(S)

ACTIVITY A B D E F LL G H - IMMEDIATE PREDECESSOR(S) None A B A C, D E D E G, H DURATION (WEEKS) 18 8 6 9 5 4 10 11 3

Step by Step Solution

3.36 Rating (165 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Critical path is A... View full answer