Question: A project has the following activities, precedence relationships, and activity durations. Draw the AOA project network. How long would it take to complete this project?
A project has the following activities, precedence relationships, and activity durations. Draw the AOA project network. How long would it take to complete this project? What is the length of the critical path?

ACTIVITY A B D E F LL G H - IMMEDIATE PREDECESSOR(S) None A B A C, D E D E G, H DURATION (WEEKS) 18 8 6 9 5 4 10 11 3
Step by Step Solution
★★★★★
3.36 Rating (165 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Critical path is A... View full answer
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
