Question: Draw the AON project network using the following information: How long would it take to complete this project? Which activities are included on the critical

Draw the AON project network using the following information:

ACTIVITY A B C D E F LL G H I J

How long would it take to complete this project? Which activities are included on the critical path?

ACTIVITY A B C D E F LL G H I J IMMEDIATE PREDECESSOR(S) I A B C, E D FL G, H G DURATION (WEEKS) 4 35 5 9 3 1 2 3 15 1