A small software development project at Krishna Dhirs firm has five major activities. The times are estimated

Question:

A small software development project at Krishna Dhir’s firm has five major activities. The times are estimated and provided in the following table.


image


a) Find the expected completion time for this project.b) What variance value would be used to find probabilities of finishing by a certain time?