Question: A small software development project has four major activities. The times are estimated and provided in the table below. (a) What is the expected completion
.png)
(a) What is the expected completion time for this project?
(b) Draw the network and state the ES, EF, LS, LF, slack in a Table.
Immediate Predecessor a m Activity 10 14 10 E, F 6 10 14 G,H
Step by Step Solution
3.40 Rating (159 Votes )
There are 3 Steps involved in it
a How to estimate expected duration and variance Calculate expected duration and variance using the ... View full answer