Question: A specialty fabrication shop has the following assembly processes for one of the products it makes: Process 1 feeds a completed component to Process 2;
A specialty fabrication shop has the following assembly processes for one of the products it makes: Process 1 feeds a completed component to Process 2; Process 2 feeds a completed assembly to Process 3; and Process 3 does the final finish work and packaging. The capacities of each process are shown above for each machine at each stage. The shop has plenty of excess labor and equipment. a. How many finished units per day can the current assembly process produce, assuming Current capacity is 4 units per day. Stages 1 and 3 are bottlenecks relative to stage 2. b. Assuming each machine requires one operator, how many machines and operators are required in each stage to produce the required output shown above?
Step by Step Solution
3.43 Rating (159 Votes )
There are 3 Steps involved in it
Stage 1 needs 3 machine... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (2 attachments)
1454_6054778c4001d_653961.pdf
180 KBs PDF File
1454_6054778c4001d_653961.docx
120 KBs Word File