Question: An assembly line with 16 tasks needs to be balanced. The line operates 7 hours a day, and the desired daily output rate is 70
An assembly line with 16 tasks needs to be balanced. The line operates 7 hours a day, and the desired daily output rate is 70 units. The total time for all the 16 tasks is 38 minutes:
1. What is the cycle time?
2. What is the theoretical minimum number of workstations required?
3. What cycle time will provide a daily output rate of 105 units?
Step by Step Solution
3.41 Rating (154 Votes )
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts